Scheduled road work for the week beginning March 21, 2010, for the Department of Design construction, Civil Division (Construction Management Branch), and Wastewater Division (Construction Management Branch) is listed below.  Road work is normally done between the hours of 8:30 AM and 3:30 PM unless otherwise noted.

Mililani
Curb Ramps at Various Locations, FY 2006 Kukolu St./Hokuula Lp./Kipapa Dr., Hokuula Lp./Kipapa Dr., Ia Pl./Kipapa Dr., Naholoholo St./Kipapa Dr., Wailoa Lp./Kanamee St./Kipapa Dr., Wailoa Lp./Naholoholo St./Kipapa Dr.:  Construction of new curb ramps, sidewalks and A.C. transition. Installation of pavement striping, markings and markers.

Estimated completion date, March 2010