Road work weekly report 3/21

Jade Eckardt

Road work weekly report

Scheduled road work for the week beginning March 21, 2010, for the Department of Design construction, Civil Division (Construction Management Branch), and Wastewater Division (Construction Management Branch) is listed below.  Road work is normally done between the hours of 8:30 AM and 3:30 PM unless otherwise noted.

Waialua

Guardail Improvements—FY2006 Phase II.  Site B:  Waialua Beach Road—66-080 Waialua Beach Road to Kiikii Stream:  Remove existing guardrails & concrete posts; provide archaeological monitoring; install object markers; install standard metal guardrail, post & spacers.

Estimated start date:  March 2010