North Shore: Road work weekly report

Jade Eckardt

Road work weekly report for the week beginning July 25, 2010, for the Department of Design construction, Civil Division (Construction Management Branch), and Wastewater Division (Construction Management Branch) is listed below.  Road work is normally done between the hours of 8:30 AM and 3:30 PM unless otherwise noted.

Waimea- Guardrail Improvements - FY 2007 Pupukea Road (Site A) and Alapio Street (Site B).  Replace existing guardrails, spacers & posts; install object markers; install erosion control matting over existing slopes. Estimated completion date:  December, 2010.