North Shore road work weekly report

Jade Eckardt

Scheduled road work for the week beginning April 11, 2010, for the Department of Design construction, Civil Division (Construction Management Branch), and Wastewater Division (Construction Management Branch) is listed below.  Road work is normally done between the hours of 8:30 AM and 3:30 PM unless otherwise noted.

Waialua

Guardail Improvements—FY2006 Phase II.  Site B:  Waialua Beach Road—66-080 Waialua Beach Road to Kiikii Stream:  Remove existing guardrails & concrete posts; provide archaeological monitoring; install object markers; install standard metal guardrail, post & spacers.
(Estimated start date:  April 2010)